Summary Explanation and Background

SUMMARY EXPLANATION AND BACKGROUND:
PROJECT DESCRIPTION / BACKGROUND

Cary Goldberg, agent for Diversified Companies., submitted a development application to amend a previously approved site plan for the subject Diversified Aviation site generally located north of Pembroke Road and west of Southwest 72 Avenue on North Perry Airport. The applicant contemplates the construction of two new airplane hangars to replace three previously approved and un-built T-hangars with associated parking, landscape, traffic circulation, lighting, and signage.

The Planning and Zoning Board previously approved the following applications for this site:

· Variance Application (ZV 2011-50) - November 10, 2011 meeting approved a parking variance for the site.
· Site Plan Application (SP 2011-18) - January 26, 2012 meeting approved the construction of airplane hangars / offices, a pilot office, fuel and plane wash and associated signage, traffic circulation, parking, and landscaping to be built in three phases.
· Site Plan Amendment Application (SP 2012-12) - September 27, 2012 meeting approved various modifications Hangar design changes and hangar additions to previously approved plan (SP 2011-18).
· Site Plan Amendment Application (SP 2014-23) - Various modifications to phase 2 and 3 hangars and the addition of the Broward College Aviation building to phase 2 (total 14 buildings over the three phase project).

To date, only the phase 1 buildings (Buildings #1, 2,,3, 4, 13) and the Broward College Building (Phase 2 - Building #14) of the approved three phase project have been constructed. The subject site plan amendment will only amend the building and site plan for phase 2 as depicted on the plan.

Phase 3 (Former Border Patrol site at south east corner of airport) will not be built as previously approved. The applicant will be required to submit a new site...