File #: 19-1418    Version: 1 Name: Reject PSPW-19-10 and Rebid as PSPW-19-15
Type: Purchase Status: Passed
File created: 11/25/2019 In control: City Commission
On agenda: 12/4/2019 Final action: 12/4/2019
Title: MOTION TO REJECT ALL BIDS FOR IFB # PSPW-19-10 "ROOF REPLACEMENT AT VARIOUS CITY BUILDINGS" AND TO AUTHORIZE THE ADVERTISEMENT OF IFB # PSPW-19-15 "REBID OF ROOF REPLACEMENT AT VARIOUS CITY BUILDINGS". 
Attachments: 1. 1. PSPW-19-15 Rebid of Roof Replacements at Various City Buildings (New), 2. 2. PSPW-19-10 Roof Replacements at Various City Buildings (Old)
Title

MOTION TO REJECT ALL BIDS FOR IFB # PSPW-19-10 "ROOF REPLACEMENT AT VARIOUS CITY BUILDINGS" AND TO AUTHORIZE THE ADVERTISEMENT OF IFB # PSPW-19-15 "REBID OF ROOF REPLACEMENT AT VARIOUS CITY BUILDINGS". 

Summary Explanation and Background

SUMMARY EXPLANATION AND BACKGROUND:

1.  On October 2, 2019, the City Commission approved the advertisement of IFB # PSPW-19-10 "Roof Replacement at Various City Buildings", which was advertised on October 8, 2019.

2.  The purpose of this solicitation was to provide roof replacement services at various City buildings.

3.  On November 12, 2019, the City opened four (4) partial bids from the following vendors:

Vendor Name

 Total Cost

Grace Roofing & Sheet Metal Enterprise

 $  70,060.00

Fullcover Roofing Systems, Inc.

 $322,754.00

Roofing Concepts Unlimited

 $338,823.45

Paul Bange Roofing

 $420,658.19

4.  At the time the proposals were tabulated, the Procurement Department deemed the bids submitted by Fullcover Roofing Systems, Inc. and Paul Bange Roofing to be non-responsive for failing to submit all of the required documents.

5.  As the remaining bids from Grace Roofing & Sheet Metal Enterprise and Roofing Concepts Unlimited/Florida, Inc. were only partilal bids, and there was not a responsive bid for every roof which needed replacement, the Public Services Department has deemed that there was inadequate amount of competition and has requested that the project be rebid.

6.  Request the City Commission to reject all proposals to IFB # PSPW-19-10 "Roof Replacement at Various City Buildings, and to authorize the advertisement of IFB # PSPW-19-15 "Rebid of Roof Replacement at Various City Buildings".

Financial Impact

FINANCIAL IMPACT DETAIL:

a)   Initial Cost: None at this time.

b)   Amount budgeted for this item in Account No: Funds are available in the following account numbers:

Location

Account Code

Carl Shechter Community Center

1-569-8001...