File #: 21-0925    Version: 1 Name: Disaster Warehouse Building Modifications-Bejar Construction, Inc.
Type: Bid Status: Passed
File created: 10/11/2021 In control: City Commission
On agenda: 10/20/2021 Final action: 10/20/2021
Title: MOTION TO AWARD IFB # PSPW-21-05 “DISASTER WAREHOUSE BUILDING MODIFICATIONS” TO BEJAR CONSTRUCTION, INC., IN THE AMOUNT NOT TO EXCEED $105,889.30, WHICH INCLUDES AN OWNER’S CONTINGENCY IN THE AMOUNT OF $9,626.30.
Sponsors: Public Services
Attachments: 1. 1. PSPW-21-05 Disaster Warehouse Building Modifications - Bejar Construction - (Vendor Executed), 2. 2. PSPW-21-05 Disaster Warehouse Building Modification - Exhibit A, 3. 3. Bejar Construction, Inc. Submittal - Exhibit B, 4. 4. PSPW-21-05 Bid Tabulation

Title

MOTION TO AWARD IFB # PSPW-21-05 “DISASTER WAREHOUSE BUILDING MODIFICATIONS” TO BEJAR CONSTRUCTION, INC., IN THE AMOUNT NOT TO EXCEED $105,889.30, WHICH INCLUDES AN OWNER’S CONTINGENCY IN THE AMOUNT OF $9,626.30.

 

Summary Explanation and Background

 

PROCUREMENT PROCESS TAKEN:

 

- Chapter 35 of the City’s Code of Ordinances is titled “PROCUREMENT PROCEDURES, PUBLIC FUNDS.”

 

- Section 35.15 defines an Invitation for Bid as “A written solicitation for competitive sealed bids with the title, date and hour of the public bid opening designated therein and specifically defining the commodities or services for which bids are sought.  The invitation for bid shall be used when the city is capable of specifically defining the scope of work for which a service is required or when the city is capable of establishing 15 precise specifications defining the actual commodities required.  The invitation for bid shall include instructions to bidders, plans, drawings and specifications, if any, bid form and other required forms and documents to be submitted with the bid.”

 

- Section 35.18 of the City's Code of Ordinances is titled "COMPETITIVE BIDDING OR COMPETITIVE PROPOSALS REQUIRED; EXCEPTIONS."

 

- Section 35.18(A) states, "A purchase of or contracts for commodities or services that is estimated by the Chief Procurement Officer to cost more than $25,000 shall be based on sealed competitive solicitations as determined by the Chief Procurement Officer, except as specifically provided herein."

 

- Section 35.19 of the City's Code of Ordinances is titled "SEALED COMPETITIVE BIDDING PROCEDURE."

 

- Section 35.19(A) states, "All sealed competitive solicitations as defined in §35.18 shall be presented to the City Commission for their consideration prior to advertisement."

 

- Section 35.21 of the City's Code of Ordinances is titled "AWARD OF CONTRACT."

 

- Section 35.21(A) of the City's Code of Ordinances is titled "City Commission approval."

 

- Section 35.21(A)(1) states, "An initial purchase of, or contract for, commodities or services, in excess of $25,000, shall require the approval of the City Commission, regardless of whether the competitive bidding or competitive proposal procedures were followed."

 

 

SUMMARY EXPLANATION AND BACKGROUND:

 

1.  On August 18, 2021, the City Commission approved the advertisement of IFB # PSPW-21-05 "Disaster Warehouse Building Modification", which was later advertised on August 24, 2021.

 

2.  The purpose of this solicitation was to make exterior/interior modifications to an existing building.

 

3.  On September 21, 2021, the City received seven (7) bids from the following vendors:

 

Vendor

Total

Bejar Construction, Inc.

$96,263.00

Maceda Contractors LLC

$153,688.00

Property Services Warranty, Inc.

$170,628.00

Conegineers Builders LLC

$190,585.23

Kalex Construction & Development Inc.

$192,270.00

Caliste Construction LLC

$195,000.00

Sun Eagle General Contractors Corp.

$199,700.00

 

4.  The Public Services Department has reviewed the bids and has deemed Bejar Construction, Inc. as the most responsive/responsible bidder.

 

5.  In addition, Bejar Construction, Inc, has also completed the Equal Benefits Form and has stated that “the Contractor currently complies with the requirements of this section."

 

6.  Request Commission to award  PSPW-21-05 "Disaster Warehouse Building Modification" to Bejar Construction, Inc., in the amount not to exceed $105,889.30, which includes an owner’s contingency in the amount of $9,626.30.

 

 

Financial Impact

FINANCIAL IMPACT DETAIL:

 

a)   Initial Cost:  $105,889.30

b)   Amount budgeted for this item in Account No: Funds for this project has been included in the proposed FY 2022 budget in account # 001-519-6001-546150-0000-000-0000 (R&M Land, Bldg.)

c)   Source of funding for difference, if not fully budgeted: Not Applicable.

d)   5 year projection of the operational cost of the project Not Applicable.

e)   Detail of additional staff requirements:  Not Applicable.