Title: MOTION TO APPROVE A CHANGE ORDER FOR THE PURCHASE AND INSTALLATION OF FLOORING FOR THE POLICE DEPARTMENT'S EAST STATION BY THE CONTRACTOR, RESOURCE 4 FLOORS, INC. IN THE AMOUNT NOT TO EXCEED $6,107.76, BRINGING THE TOTAL OF PURCHASE ORDER # 20211649 TO AN AMOUNT NOT TO EXCEED $81,721.34.
Sponsors: Police
Attachments: 1. 1. Moisture Mitigation Quote, 2. 2. Sourcewell Contract Pricing, 3. 3. Sourcewell Contract, 4. 4. Commission Approval 8-4-21, 5. 5. Purchase Order # 20211649
Title

MOTION TO APPROVE A CHANGE ORDER FOR THE PURCHASE AND INSTALLATION OF FLOORING FOR THE POLICE DEPARTMENT'S EAST STATION BY THE CONTRACTOR, RESOURCE 4 FLOORS, INC. IN THE AMOUNT NOT TO EXCEED $6,107.76, BRINGING THE TOTAL OF PURCHASE ORDER # 20211649 TO AN AMOUNT NOT TO EXCEED $81,721.34.

Summary Explanation and Background

PROCUREMENT PROCESS TAKEN:

- Chapter 35 of the City’s Code of Ordinance is titled “PROCUREMENT PROCEDURES, PUBLIC FUNDS.”

- Section 35.18 of the City's Code of Ordinances is titled "COMPETITIVE BIDDING OR COMPETITIVE PROPOSALS REQUIRED; EXCEPTIONS."

- Section 35.18(C) states that "Only the following situations are exempt from the competitive bid and competitive proposal requirements of this section:"

- Section 35.18(C)(5) of the City’s Code of Ordinances, “Commodities or services that are the subject of contracts with the state its political subdivisions or other governmental entities including the United States Government, are exempt from the competitive procurement process.”

- Section 35.21 of the City's Code of Ordinances is titled "AWARD OF CONTRACT."

- Section 35.21(A) of the City's Code of Ordinances is titled "City Commission Approval."

- Section 35.21(A)(1) states, "An initial purchase of, or contract for, commodities or services, in excess of $25,000, shall require the approval of the City Commission, regardless of whether the competitive bidding or competitive proposal procedures were followed."- Section 35.28 of the City's Code of Ordinances is titled "CHANGE ORDERS."

- Section 35.28 of the City's Code of Ordinances is titled "CHANGE ORDERS."

- Section 35.28(B) states that "Notwithstanding the provisions of (A) above, the City Manager is not authorized to approve a change order without authorization of the City Commission where the initial purchase required the City Commission's approval and where the sum of all change orders issued under the contract exceeds 5% of the original contract amount or $25,000...